AI Security Planner

Demo data. Any changes do not save and are reset on refresh.

Schedule and capacity

At risk, needs staffingOff-track or blockedOn plan, capacity coveredAt risk, needs rescheduling30 extra20 extra10 extraBalanced10 needed20 needed30 needed60 early40 early20 earlyOn plan20 late40 late60 late
Capacity balance (person-days)Schedule variance (calendar days)

Recommendations

Recommendations requiring attention
Actions
All / London
Ransomware ResilienceProgram
USD 180M
Resolve “Test restoration of critical services” with Recovery lead. Agree a recovery sequence for the remaining work and confirm achievable milestone dates.Needed by Nov 03, 2026. Forecast finish 2027-03-19 is 42 days after the target.
All / London
Ransomware ResilienceProgram
USD 180M
Resolve the technical dependency, then retest affected work.Needed by Feb 05, 2027. RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
All / London
Ransomware ResilienceProgram
USD 180M
Confirm the external owner, commitment, and date.Needed by Feb 05, 2027. RR-18 finishes on Mar 19, 2027, 42 days after its Feb 05, 2027 target.
All / Chicago
Ransomware ResilienceProgram
USD 180M
Close the 6.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by Feb 19, 2027. 6.5 person-days short of the capacity needed by 2027-02-19. Forecast finish 2027-04-09 is 49 days after the target.
All / Sydney
Ransomware ResilienceProgram
USD 180M
Close the 13.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by Mar 05, 2027. 13.5 person-days short of the capacity needed by 2027-03-05. Forecast finish 2027-04-23 is 49 days after the target.
All / Chicago
Identity Access ModernizationProgram
USD 95M
Close the 4.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by May 21, 2027. 4.5 person-days short of the capacity needed by 2027-05-21. Forecast finish 2027-07-02 is 42 days after the target.
  1. All / London
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Resolve “Test restoration of critical services” with Recovery lead. Agree a recovery sequence for the remaining work and confirm achievable milestone dates.Needed by Nov 03, 2026. Forecast finish 2027-03-19 is 42 days after the target.
  2. All / London
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Resolve the technical dependency, then retest affected work.Needed by Feb 05, 2027. RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
  3. All / London
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Confirm the external owner, commitment, and date.Needed by Feb 05, 2027. RR-18 finishes on Mar 19, 2027, 42 days after its Feb 05, 2027 target.
  4. All / Chicago
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Close the 6.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by Feb 19, 2027. 6.5 person-days short of the capacity needed by 2027-02-19. Forecast finish 2027-04-09 is 49 days after the target.
  5. All / Sydney
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Close the 13.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by Mar 05, 2027. 13.5 person-days short of the capacity needed by 2027-03-05. Forecast finish 2027-04-23 is 49 days after the target.
  6. All / Chicago
    Identity Access ModernizationProgram
    USD 95M

    Recommendation

    Close the 4.5 person-day shortfall: confirm capacity, reduce remaining scope, or agree a revised target.Needed by May 21, 2027. 4.5 person-days short of the capacity needed by 2027-05-21. Forecast finish 2027-07-02 is 42 days after the target.