AI Security Planner

Demo data. Any changes do not save and are reset on refresh.

Ransomware Resilience

Organization
Demo
Unit
Not attached
Site
London

Gantt

Current planGenerated baselineTodayCritical pathComplete
RR-P1Govern ransomware resilience
In progress
RR-P1-M01Set program ownership and decisions
CompleteActual completionNot scheduled
RR-P1-M02Define critical services and data2 tasks, 3 subtasks
Complete
RR-P1-M02-T1Confirm Tier 1 service owners
Complete
RR-P1-M02-T2Approve the critical-service dependency map
Complete
RR-P1-M03Approve recovery priorities and objectives
Complete
RR-P1-M15Operationalize the ransomware response playbook
Planned
RR-P1-M16Confirm the executive crisis decision process
Planned
RR-P2Prepare recovery access and restoration
Blocked
RR-P2-M05Separate daily and privileged administration
Complete
RR-P2-M06Require strong authentication
Complete
RR-P2-M07Define recovery access procedures
Complete
RR-P2-M12Establish isolated backup copies1 task, 2 subtasks
Complete
RR-P2-M12-T1Validate isolated backup policy coverage
Complete
RR-P2-M17Test restoration of critical services1 task, 3 subtasks
Blocked
RR-P2-M17-T1Restore Tier 1 identity services in isolation
Planned
USR-01Validate clean-room identity recovery access
Planned
RR-P3Design resilient service boundaries
Complete
RR-P3-M04Design resilient service architecture
Complete
RR-P3-M11Segment critical networks and services
Complete
RR-P4Reduce, detect, and exercise ransomware risk
Blocked
RR-P4-M08Set endpoint detection and isolation coverage
Complete
RR-P4-M09Prioritize vulnerability remediation
Complete
RR-P4-M10Restrict and monitor privileged access
Complete
RR-P4-M13Define detection and escalation procedures
In progress
RR-P4-M14Test alert triage and isolation
In progress
RR-P4-M18Run and review a ransomware exercise1 task, 3 subtasks
Blocked
RR-P4-M18-T1Run the executive ransomware exercise
Planned
Govern ransomware resilience
Forecast
November 27, 2026
RR-P1-M02, Define critical services and data
Forecast
August 21, 2026
Generated baseline
August 21, 2026
RR-P1-M02-T1, Confirm Tier 1 service owners
Forecast
August 21, 2026
RR-P1-M02-T2, Approve the critical-service dependency map
Forecast
August 21, 2026
RR-P1-M03, Approve recovery priorities and objectives
Forecast
August 28, 2026
Generated baseline
August 28, 2026
RR-P1-M15, Operationalize the ransomware response playbook
Forecast
November 20, 2026
Generated baseline
September 11, 2026
RR-P1-M16, Confirm the executive crisis decision process
Forecast
November 27, 2026
Generated baseline
September 18, 2026
Prepare recovery access and restoration
Forecast
February 26, 2027
RR-P2-M05, Separate daily and privileged administration
Forecast
October 9, 2026
Generated baseline
October 9, 2026
RR-P2-M06, Require strong authentication
Forecast
October 16, 2026
Generated baseline
October 16, 2026
RR-P2-M07, Define recovery access procedures
Forecast
October 23, 2026
Generated baseline
October 23, 2026
RR-P2-M12, Establish isolated backup copies
Forecast
December 11, 2026
Generated baseline
December 11, 2026
RR-P2-M12-T1, Validate isolated backup policy coverage
Forecast
December 11, 2026
RR-P2-M17, Test restoration of critical services
Forecast
February 26, 2027
Generated baseline
January 29, 2027
RR-P2-M17-T1, Restore Tier 1 identity services in isolation
Forecast
February 26, 2027
USR-01, Validate clean-room identity recovery access
Forecast
December 18, 2026
Generated baseline
January 15, 2027
Design resilient service boundaries
Forecast
November 27, 2026
RR-P3-M04, Design resilient service architecture
Forecast
October 2, 2026
Generated baseline
October 2, 2026
RR-P3-M11, Segment critical networks and services
Forecast
November 27, 2026
Generated baseline
November 27, 2026
Reduce, detect, and exercise ransomware risk
Forecast
March 19, 2027
RR-P4-M08, Set endpoint detection and isolation coverage
Forecast
October 30, 2026
Generated baseline
October 30, 2026
RR-P4-M09, Prioritize vulnerability remediation
Forecast
November 6, 2026
Generated baseline
November 6, 2026
RR-P4-M10, Restrict and monitor privileged access
Forecast
November 13, 2026
Generated baseline
November 13, 2026
RR-P4-M13, Define detection and escalation procedures
Forecast
December 11, 2026
Generated baseline
December 25, 2026
RR-P4-M14, Test alert triage and isolation
Forecast
December 18, 2026
Generated baseline
January 1, 2027
RR-P4-M18, Run and review a ransomware exercise
Forecast
March 19, 2027
Generated baseline
February 12, 2027
RR-P4-M18-T1, Run the executive ransomware exercise
Forecast
March 19, 2027

Recommendations

Recommendations requiring attention
Actions
London
Ransomware ResilienceProgram
USD 180M
Resolve “Test restoration of critical services” with Recovery lead. Agree a recovery sequence for the remaining work and confirm achievable milestone dates.Forecast finish 2027-03-19 is 42 days after the target.
Nov 04, 2026
London
RR-P02 Prepare recovery access and restorationProject
USD 180M
Resolve the technical dependency, then retest affected work.RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
Feb 05, 2027
London
RR-P04 Reduce, detect, and exercise ransomware riskProject
USD 180M
Confirm the external owner, commitment, and date.RR-18 finishes on Mar 19, 2027, 42 days after its Feb 05, 2027 target.
Feb 05, 2027
  1. Site
    London
    Ransomware ResilienceProgram
    USD 180M

    Recommendation

    Resolve “Test restoration of critical services” with Recovery lead. Agree a recovery sequence for the remaining work and confirm achievable milestone dates.Forecast finish 2027-03-19 is 42 days after the target.
    NeededNov 04, 2026
  2. Site
    London
    RR-P02 Prepare recovery access and restorationProject
    USD 180M

    Recommendation

    Resolve the technical dependency, then retest affected work.RR-17 finishes on Feb 26, 2027, 21 days after its Feb 05, 2027 target.
    NeededFeb 05, 2027
  3. Site
    London
    RR-P04 Reduce, detect, and exercise ransomware riskProject
    USD 180M

    Recommendation

    Confirm the external owner, commitment, and date.RR-18 finishes on Mar 19, 2027, 42 days after its Feb 05, 2027 target.
    NeededFeb 05, 2027